The construction team has been hard at work over the past several weeks. The weather continues to be in favor of the construction work being done with pleasant day-time temperatures and sunshine. Clay block walls have started to be constructed and with the good weather the team of contractors is managing to lay up approximately 4,160 blocks per day. Their goals is to accelerate construction so that the building can be under roof by the time heavy snow begins to fall in the area.
Exterior walls at administration wing getting started.
Start of exterior walls at gymnasium wing.
Gymnasium wing walls nearing first level of completion. Next step is pouring an intermediate bond beam and them continuing vertical with columns and clay block infill.
"Front" of the school. The gymnasium wing in the background and the lobby in the foreground. Rough site grading and back fill in progress.