Phase 1 construction of the KLA began on September 17, 2015 with the signing of a construction contract with ProArt (Kosovar owned design/build company) and Global Neighbors. Within days clearing of land, excavation of foundations and site fencing construction was started. In late September through early October the following construction activities were completed: footers were poured, grade beams formed and poured and the concrete pads were poured for the administration wing and gymnasium wing.
Concept model of the KLA - Phase 1 includes gymnasium, lobby, administration, support spaces (music, library and media center, lunch room, kitchen, teachers room, boiler room and delivery area). Phase 2 includes a three-story classroom wing and athletic fields.
Land clearing and building layout.
Grade bream forms.
Pouring concrete grade beams.
Backfill and compaction of building pad.
Installation of in-slab plumbing lines.
Pouring of building pad at gymnasium wing.
Excavation of lobby area between administration and gymnasium wings.
Excavation of boiler room wing.
Forming of columns in administration wing.
Delivery of clay block for exterior walls.